Before the investment programme started our targets were:
- By the end of the 5-year investment programme to have made 19957 improvements
In the two years to date we have already made close to 10,000 improvements
- All homes to reach the Decent Homes standard or beyond
At the start of the programme 986 out of 5237 homes met the standard
At the start of March 2010 there are now 2000 homes that meet the standard
- ll homes to have at least one improvement by March 2011
We are on track to have completed at least one improvement to 5,000 homes and the remaining homes (around 250) have been offered improvements which will take place in 2011/12 subject to access arrangements.
These are the improvement projects which are underway:
New upvc windows and front doors
Contractors: Allten Windows and Wrekin Windows
Started June 2009
Due to complete July? 2011
Stanley Grove estate external improvements (roofing, pointing, replacement of back boilers)
Contractor: Henry Boot Ltd
Started October 2009
Due to complete February 2011
Hampden Crescent estate external improvements (insulation, windows, replacement of porches)
Contractor: P.Casey Ltd
Started September 2009
Due to complete July 2011
Anson estate external improvements (roofing, pointing, replacement of back boilers )
Contractor: BAAS Construction
Started October 2009
Due to complete March 2011
Miscellaneous properties internal improvements (kitchens, bathrooms, rewires, boilers)
Contractors: Jamiesons, McCoskers
Started October 2009
Due to complete March 2011
Gorton North Central and Ryder Brow estate
Kitchens, bathrooms, some rewires where required
Contractor: P.Casey Ltd
Started June 2010
Due to complete October 2011
Ardwick Cotter Street area & Longsight Plymouth Grove area
Kitchens, bathrooms, some rewires where required
Contractor: Henry Boot Ltd
Started May 2010
Due to complete July 2011
Gorton Park estate
Kitchens, bathrooms, some rewires where required
Contractor: Bullock Construction
Started May 2010
Due to complete May 2011
Gorton South and Levenshulme dispersed properties
Kitchens, bathrooms, some rewires where required
Contractor: Lovell Partnerships Ltd
Started October 2010
Due to complete June 2011
New boilers to replace communal boilers
Various cottage flats blocks
Contractors: Aqua Interiors, Mitie, Heatcraft, Murphys
Started: November 2010
Due to complete: September 2011
Replacement of old inefficient boilers where necessary
All areas
Contractors: Aqua Interiors, Mitie, Heatcraft, Murphys
Started: November 2010
Due to complete: March 2012
Lift replacement and new lifts to serve all floors
Platt Court, Worsley Court, Abbey Court, Cornwall Court
Contractor: Oakland Excelsior Ltd
Started: January 2011
Due to complete: August 2011
We have also made a start on our £13m environmental programme, tackling hot spots in various areas following consultation with local residents.
A major scheme of highway improvements is starting at the Anson Estate in summer 2011. This work is being carried out in partnership with MCC Highways. We have agreed to extend the scope of their planned works and contribute financially to an enhanced scheme.