How have we done so far?

Before the investment programme started our targets were:

  • By the end of the 5-year investment programme to have made 19957 improvements

In the two years  to date  we have already made close to 10,000  improvements

  • All homes to reach the Decent Homes standard or beyond

At the start of the programme 986 out of 5237 homes met the standard

At the start of March 2010 there are now 2000 homes that meet the standard

  • ll homes to have at least one improvement by March 2011

We are on track to have completed at least one improvement to 5,000 homes and the remaining homes (around 250) have been offered improvements which will take place in 2011/12 subject to access arrangements.

These are the improvement projects which are underway:

New upvc windows and front doors

Contractors: Allten Windows and Wrekin Windows

Started June 2009

Due to complete July?  2011

Stanley Grove estate external improvements (roofing, pointing, replacement of back boilers)

Contractor: Henry Boot Ltd

Started October 2009

Due to complete February 2011

Hampden Crescent estate external improvements (insulation, windows, replacement of porches)

Contractor: P.Casey Ltd

Started September 2009

Due to complete July 2011

Anson estate external improvements (roofing, pointing, replacement of back boilers )

Contractor: BAAS Construction

Started October 2009

Due to complete March 2011

Miscellaneous properties internal improvements (kitchens, bathrooms, rewires, boilers)

Contractors: Jamiesons, McCoskers

Started October 2009

Due to complete March 2011

Gorton North Central and Ryder Brow estate

Kitchens, bathrooms, some rewires where required

Contractor: P.Casey Ltd

Started June 2010

Due to complete October 2011

Ardwick Cotter Street area & Longsight Plymouth Grove area

Kitchens, bathrooms, some rewires where required

Contractor: Henry Boot Ltd

Started May 2010

Due to complete July 2011

Gorton Park estate

Kitchens, bathrooms, some rewires where required

Contractor: Bullock Construction

Started May 2010

Due to complete May 2011

Gorton South and Levenshulme dispersed properties

Kitchens, bathrooms, some rewires where required

Contractor: Lovell Partnerships Ltd

Started October 2010

Due to complete June 2011

New boilers to replace communal boilers

Various cottage flats blocks

Contractors: Aqua Interiors, Mitie, Heatcraft, Murphys

Started: November 2010

Due to complete: September 2011

Replacement of old inefficient boilers where necessary

All areas

Contractors: Aqua Interiors, Mitie, Heatcraft, Murphys

Started: November 2010

Due to complete: March 2012

Lift replacement and new lifts to serve all floors

Platt Court, Worsley Court, Abbey Court, Cornwall Court

Contractor: Oakland Excelsior Ltd

Started: January 2011

Due to complete: August 2011

We have also made a start on our £13m environmental programme, tackling ‘hot spots’ in various areas following consultation with local residents.

A major scheme of highway improvements is starting at the Anson Estate in summer 2011.  This work is being carried out in partnership with MCC Highways.  We have agreed to extend the scope of their planned works and contribute financially to an enhanced scheme.

 

Improvement Programme
  • Eastlands Homes Investment Programmes
  • The 2009 Transfer Promises
  • Year Eight Update
  • Decent Homes
  • Meet the Investment Team
  • Eastlands Homes Standard
  • How have we done so far?
  • Customer Involvement
  • Customer Satisfaction
  • Working with Contractors
  • Adapting the programme to meet customers needs
  • What will we do next?
  • Looking ahead
  • What else should I know?